| # | Objective | Status | Owner (Dept) | Dependencies | Target |
|---|---|---|---|---|---|
| 1 | Get Permissions All statutory approvals for site start |
Blocked | PM | Govt approvals | TBD |
| 2 | Plinth — Villas 3, 4, 5, 6 Foundation + plinth for first 3–4 houses ASAP |
In Progress | DI BI | Permissions, Serie drawings, structural from McdBerl | ASAP post-permissions |
| 3 | Compound Wall Perimeter security wall |
Not Started | DI Site | Boundary survey, design approval | TBD |
| 4 | STP Setup Sewage treatment plant |
Not Started | DI BI | SPT/Soda specs, location finalization | TBD |
| 5 | Nursery Setup On-site plant nursery for landscaping |
Not Started | Site | Landscape consultant input | TBD |
| 6 | Site Mobilisation Labour, equipment, temporary facilities |
In Progress | Site PM | Permissions, storage area ready | TBD |
| 7 | Road + Tree Cutting & Removal Access road prep + selective tree removal |
Not Started | Site | Permissions, landscape plan | TBD |
| 8 | Submission Drawings — Villa 5 & 6 Villa 4 complete; 5 & 6 pending |
Blocked | DI | Serie / MCD coordination | Urgent |
| 9 | Una & Roy Foundation Fast-track foundation for storage area conversion |
In Progress | DI BI | Structural drawings, site access | Priority |
| Objective | Design Integration | Build Integration | Site Mgmt | Project Mgmt |
|---|---|---|---|---|
| Permissions | — | — | — | OWNER |
| Plinth (Villas 3–6) | Drawings, specs, coordination | BOQ, quotations, materials | Execution | Timeline, review gates |
| Compound Wall | Design + BOQ | Quotation | Execution | — |
| STP Setup | Specs from SPT/Soda | Vendor selection + costing | Installation | — |
| Nursery | Plant schedule + location | — | Setup + maintenance | — |
| Mobilisation | — | — | OWNER — labour, equip, temp | Budget approval |
| Road + Tree Removal | Landscape input | — | Execution | Permission clearance |
| Villa 5 & 6 Drawings | OWNER — Serie/MCD coordination | — | — | — |
| Una & Roy Foundation | Structural drawings | Material + BOQ | Execution | — |
| Phase | Start | End | Status | Key Dependency |
|---|---|---|---|---|
| TRG Full Roof Complete roof across all wings |
~18 Mar | ~2 Apr | In Progress | Payment confirmed + vendor mobilised |
| Stone Flooring Room-by-room, Wing A ground first (~3d/room) |
~1 Apr | ~15 May | Blocked | Stone work order NOT ISSUED — OVERDUE |
| Base Plaster Room-by-room after frames installed |
~10 Apr | ~30 May | Not Started | Frames installed per room |
| Door & Window Frames Mashur — ~1 month production after sign-off |
~15 Apr | ~30 May | At Risk | Mashur samples need sign-off this week |
| Carpentry Wardrobes, kitchen, fixed furniture |
~17 Apr | ~4 Jun | Blocked | ALL drawings by 25 Mar — CRITICAL |
| Stone Carcasses AC cabinets, cupboards, kitchen units |
~17 Apr | ~4 Jun | Blocked | Drawings + stone delivery pending |
| Landscaping All planting before monsoon |
~25 Apr | ~25 May | Not Started | Louis concept draft needed |
| Finishing Lime Plaster Keyur Bhai's team — final polished finish |
Late May | July | Not Started | Base plaster cured, rooms dust-free, no drilling |
| Furniture + Electrical + HVAC AC units, lights, hardware — parallel with plaster |
Jun | Jul | Not Started | Room-by-room handover from Keyur Bhai |
| # | Question | Why It Matters | Owner |
|---|---|---|---|
| A | Stone work order: issued? Vendor + delivery schedule confirmed? | Without this, flooring start ~1 Apr is dead | Clive / Akshay |
| B | Rishi's Sam visit debrief: what was approved 26 Feb? What's open? | Defines which actions are unlocked | Rishi |
| C | Cabinetry drawings: is Sam's team on track for 25 Mar? | Blocks carpentry + May readiness | Sam / Rishi |
| D | Carpentry vendor: who is executing? Source identified? | Need confirmed vendor + work order by 30 Mar | Rishi |
| E | Keyur Bhai: confirmed availability from ~25 May? | His arrival = finishing plaster starts | Akshay |
| F | STP / pool pump room: OC required? Can we engage Aga? | Long-lead if OC needed | Rishi / Akshay |
| G | Build Integration role: any progress? | Root cause of repeated procurement errors | Akshay |
| H | Landscape concept from Louis: engaged? | Install window ~25 Apr – 25 May | Rishi / Vrinda |
| Phase / Milestone | Start | End | Status | Key Dependency |
|---|---|---|---|---|
| PHASE 1 — FOUNDATIONS TO PLINTH (2.5 months) | ||||
| Submit budget + excavation plan to owners Immediate deliverable — unlocks everything |
NOW | Mar 25 | In Progress | Owner buy-in confirmed; need budget doc |
| Site mobilisation + excavation Earthwork, soil testing, excavation for foundations |
~Apr 1 | ~Apr 20 | Not Started | Budget approval from owners |
| Foundation work Footings, grade beams, PCC |
~Apr 20 | ~May 15 | Not Started | Structural drawings, excavation complete |
| Plinth level complete Plinth walls, backfill, plinth beam |
~May 15 | Jun 1 | Not Started | Foundation complete, MEP first fix coordinated |
| PHASE 2 — STRUCTURE + ROOF (6 months) — designed in parallel with Phase 1 | ||||
| Superstructure — walls, columns, beams Full structural frame |
Jun 2026 | Sep 2026 | Not Started | Plinth complete; full structural + MEP drawings |
| Roof structure + installation Roof system TBD — coordinate with material selection |
Sep 2026 | Dec 2026 | Not Started | Superstructure complete; roof design finalised |
| PHASE 3 — INTERIORS + FINISHING (5 months) | ||||
| Interior finishing — plaster, flooring, doors/windows | Jan 2027 | Mar 2027 | Not Started | Roof up; all interior designs finalised |
| MEP final fix — electrical, plumbing, HVAC | Feb 2027 | Apr 2027 | Not Started | Interior shell complete |
| Furniture, fixtures, landscaping, handover | Apr 2027 | May 2027 | Not Started | All finishing complete |
| Parameter | Value | Notes |
|---|---|---|
| Total site area | 17,500 sqm | 3 survey numbers combined |
| CRZ area | 4,330 sqm | No permanent construction. Gardens, open areas, temporary structures only |
| Effective area (FAR permissible) | 13,730 sqm | 17,500 – 4,330 + adjustments = 13,730 |
| Available FAR | 10,500 sqm | Total buildable floor area across all development |
| Development zone | S23 + S29/2 | ~14,650–15,150 sqm land area → apartments + gardens |
| Clubhouse zone | S29/1 | 2,950 sqm → clubhouse + sports + F&B + membership |
| # | Deliverable | Status | Owner | Dependencies |
|---|---|---|---|---|
| 1 | Complete area statement FAR utilisation, unit breakdown, built-up vs open, CRZ mapping |
In Progress | DI Serie + SPF | CRZ boundaries confirmed, FAR calculations verified |
| 2 | Site masterplan / concept layout Apartment block placement, clubhouse location, access, parking, gardens |
In Progress | DI Serie | Area statement, site survey/topo data |
| 3 | Apartment typology + unit mix 1BHK/2BHK/3BHK ratio, sizes, number of units, floor count |
Not Started | DI Serie + Akshay | Market positioning decision, FAR allocation |
| 4 | Clubhouse program + layout Sports courts, pool, gym, F&B spaces — fit within 2,950 sqm |
Not Started | DI Serie + Akshay | Program brief finalised |
| 5 | Basic 3D renders / visuals Enough to communicate the vision to landowner — not detailed |
Not Started | DI Serie | Concept layout locked |
| 6 | CRZ landscape / open space concept How the 4,330 sqm CRZ becomes a feature — gardens, walkways, open areas |
Not Started | DI Serie | CRZ boundaries mapped; masterplan concept |
| 7 | Preliminary financial feasibility Rough construction cost, revenue estimate, viability check |
Not Started | PM Akshay + SPF | Unit mix + area statement finalised |
| 8 | Landowner presentation pack Polished deck: feasibility + concepts + renders + area statement + financials |
Not Started | PM Akshay | All above deliverables complete |
| Work Package | V1 Estimate | Status | Notes |
|---|---|---|---|
| Roofing Structure Over courts — 3 options under evaluation |
₹60–90L | Option TBC | Tensile likely +30% vs metal |
| padel Courts × 2 Covered courts |
₹30–45L | Quotes Pending | Michezo in; Sky Paddle + Babolat pending |
| Volleyball Courts × 2 | ₹12–18L | In Michezo Quote | Confirm multi-sport surface spec |
| Pickleball Courts × 2 | ₹10–15L | Budget-Dependent | May be cut if over ceiling |
| Container Facilities × 3 Changing rooms, toilets, juice bar |
~₹57L | Base Cost Received | ₹19L/container; interiors in progress |
| MEP (Electrical + Plumbing) | ₹15–25L | Drawings March | New electrical room + solar backup |
| Parking Area (60–70 cars) | ₹12–18L | Costing In Progress | Laterite + pea gravel; GI mesh boundary |
| Landscaping + Walkways | ₹8–12L | Louis Sketching | Awaiting sketch + costing |
| Cafe / F&B Infrastructure | ₹10–15L | Scope TBD | Container or built; post-court confirmation |
| CrossFit / Functional Fitness | ₹5–8L | Approved | Equipment + flooring — not yet costed |
| Running Track | ₹8–12L | Feasibility Pending | Subject to field size confirmation |
| Site Survey + Soil Work | ₹2–4L | CRITICAL PATH | Unblock immediately — blocks everything |
| Contingency (10%) | ₹18–22L | Reserve | Do not allocate until base confirmed |
| TOTAL | ~₹2.0–2.4Cr | Needs Consolidation | Must close within ₹2.2Cr ceiling |
| # | Action | Owner | Deadline | Status |
|---|---|---|---|---|
| A | Thursday call: walk Adheesh through lawyer brief (v2) | Akshay + Arup + Adheesh | This Thursday | In Progress |
| B | Adheesh to produce revised 2028 Agreement draft | Adheesh (Halo Partners) | 1 week post-call | Not Started |
| C | Provide approved SPF Masterplan (Feb 2026) for Annexure A | Akshay / Ekta | With revised draft | Not Started |
| D | Confirm signatory names — Foundation + Society side | Akshay + Arup | Before final draft | Not Started |
| E | Akshay + Arup review revised draft | Akshay + Arup | 2 weeks post-call | Not Started |
| Frequency | Meeting | Who | Output |
|---|---|---|---|
| Weekly Monday | Design Integration Stand-up | Akshay + Ekta + Vrinda + Dinesh | Updated action list + blockers flagged |
| Bi-weekly | Budget Review | Akshay + Arup + Dinesh | Budget tracker updated; decisions flagged to Raju |
| As needed | Raju Update | Akshay + Arup | 1-page decision brief; never surprise him |
| Ongoing | Consultant Follow-up (written) | Ekta (primary) | Email with deliverable + deadline after every call |
Akshay, Rishi, Vrinda, Saurab sit together to define: objectives, phases, timelines, and dependencies. This is NOT any single department's job — it's a collective exercise.
Each objective gets mapped to which departments are involved and what each department's responsibility is (the Objective × Department Matrix).
Each department (DI, BI, Site, PM) owns their lane. They break their responsibilities into tasks with: consultant/vendor, status, dates needed, and dependencies.
Every consultant/vendor tracked with: what's needed from them, by when, current status, and which department is coordinating.
The goal is to reduce "WhatsApp chaos" by creating structured execution packages. Each objective should have: scope, drawings list, BOQ/estimates, method statements, checklists, and review gates.
Design Integration owns the coordination — not the execution. Their job is to make sure everyone knows what's required of them and when. Whether DI does it themselves or delegates is a bandwidth question, not a role question.
Project Master Plan is collective. DI doesn't set timelines alone. The core team (Akshay, Rishi, Vrinda, Saurab) defines the master plan together. Once set, each department knows their lane and pushes forward.